Great Solar Upgrade – Day #2

Day #2 come and gone!

Day #1 was without incident, problem, or even a hiccup…for which I am grateful. Day #2…not so much…but not bad at all.

First off let me explain that I had the project broken down into phases.

Phase #1 – Preparation: Getting all my parts and equipment purchased, on-site, any pre-work completed on them, get generator ready, gasoline purchased, and tools either purchased or centralized.

Phase #2 – Deconstruction: Remove all the old system components, organize, confirm that they are still serviceable, and replace/repair as needed.

Phase #3 – AC Re-Do: Replace the AC main disconnect fuses with circuit breaker, combine/join AC main panel, AC main disconnect, transfer switch into a single unit, rewire the generator to transfer switch wiring for later addition of a 240vAC inlet, and hook-up temporary fix to run generator.

Phase #4 – Construction: Add Hardee Cement Board to walls.

Phase #5 – Build Out DC: Literally rebuild the entire DC side of the system, including all the new gear.

Phase #6 – Configure: Charge up the new battery to same voltage as the existing two batteries. Using Victron software to configure and fine-tune the system.

Phase #7 – PVs (solar panels): Add another string (245w X 3S) to Array #2 and #3 and replace 8 x 100w PVs on Array #1 with 6 x 245w PVs (3S2P).

Phase #8 – Take a freaking week off and do nothing but enjoy the new system!

Phases #1 – #4 are complete, phase #5 is well underway. I did hit a snag and had to rebuild and relocate the AC main panel, AC main disconnect, and the transfer switch. That added an extra 2 hours to the process…rebuilding what had already been done. But, I had to move it to clean-up the layout and give proper access to the transfer panel and ensure the right clearance around Inverter #1. Other than that, the 13-hour day #2 went well.

I gotta post this, eat some breakfast, and get back after it 🙂

At the beginning of Day #2 –

At the end of Day #2 –

Donate-3


Related Articles –
 2009 - 2023 Copyright © AHTrimble.com ~ All rights reserved
No reproduction or other use of this content 
without expressed written permission from AHTrimble.com
See Content Use Policy for more information.

9 thoughts on “Great Solar Upgrade – Day #2

  1. Pingback: Great Solar Upgrade – Day #8 | A.H. Trimble - Emergency preparedness information for disasters and grid-down

  2. Pingback: Great Solar Upgrade – Day #7 – IT WORKS ! ! | A.H. Trimble - Emergency preparedness information for disasters and grid-down

  3. Pingback: Great Solar Upgrade – Day #6 | A.H. Trimble - Emergency preparedness information for disasters and grid-down

  4. Pingback: Great Solar Upgrade – Day #5 | A.H. Trimble - Emergency preparedness information for disasters and grid-down

  5. Pingback: Great Solar Upgrade – Day #4 | A.H. Trimble - Emergency preparedness information for disasters and grid-down

  6. Pingback: Great Solar Upgrade – Day #3 | A.H. Trimble - Emergency preparedness information for disasters and grid-down

  7. Pingback: Great Solar Upgrade – Day #1 | A.H. Trimble - Emergency preparedness information for disasters and grid-down

    • You got that right Doug!
      I am finding little mistakes I made along the way…thankfully nothing major. But they all get corrected, improved, etc.
      And Yeah…when the power goes out I am the one I have to call.
      Oh wait, my power doesn’t go out 🙂

      Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s